The completion of Zuidzicht will start in March 2020
29 January 2020
Royal FloraHolland is building an attractive, healthy and safe work environment for its employees that meets today’s requirements. That is why we are converting our offices into high-quality co-working spaces with meeting rooms for colleagues, growers and customers.
In the past months, the old office Zuidzicht in Aalsmeer has been stripped and the round extension was glazed for the most part. Casco will be finished until early March 2020, after which the completion will begin!
Update Construction Aalsmeer
The street scene at our location in Aalsmeer has changed a lot since the festive kick-off of the construction in May 2019. Now that the new office has its impressive half-round shape, you can start imagining what it will be like to co-work here.
All foundation piles have now been placed, all floors have been created, part of the central staircase in the new atrium has been put into place and the round south facade has been glazed for the most part.
But a lot of less visible work has also been carried out, such as the cable and pipe work, the electrical installation and the work in the old part of the Zuidzicht office and placing a temporary roof over the atrium to shelter it from the rain.
Which work will be done in the near future?
BAM Construction will be finishing the work until early March. BAM will soon replace the temporary roof cowl above the atrium with the final roof, construct the last part of the staircase and cast the screeds. They will also be finishing the work on the facades soon.
Completion will start once BAM finishes this work. During the completion process we will finish the floors and the ceilings, construct partitions for meeting and work rooms and construct the (dishwashing) kitchen and the restaurant. All fixed furniture (reception counters, pantries, etc.) and all loose furniture will be placed in the new office. In addition to this, we will be establishing all other (IT) facilities.
Timelines & milestones
- Building wind and& waterproof February 2020
- Completion Casco Zuidzicht March 2020
- Start completion work Building-in Package & outside area March 2020
- Outside area finished April/May 2020
- Commissioning Construction Aalsmeer July/August 2020